While Cari and I hung around inside with the kids and my mum, Derald, Pam, Shawn and Brian got to work. Pam did us a huge favor and cleaned up the mess we had in the garage, and got things organized and tidy. She also tidied up and cleaned up some more in the basement while the guys worked on siding the back wall of the garage.
Since the last post, we had our meeting with the electrician. He's going to let us hang boxes and cut holes in the studs for the wires to help us save a bit on labor. So we headed down to Menards to get some supplies, and we had to go back to change to a heavier duty electrical box after the electrician said he prefers a certain kind.
Last Friday, my in-laws came back again to help us work on some more siding. This time Pam was given a crash course on installing the siding, and she was Shawn's help, while Derald cut boards and painted more siding as well. By the end of the day Saturday, the NW wall of the garage was done!
So the solution was to frame extra support inside the garage to help transfer the roof load more onto the footing.So you can see the new studs framing around the garage door openings and supporting the extra LVL Beams that are adding support directly under the trusses above the opening. The guys did a wonderful job, and my FIL with his woodworking skills used our table saw to cut out grooves on that bottom 2x6 to fit over the j-bolts that bolt the wall to the footing. Pam and I helped a bit to hold up the vertical 2x4's while Shawn and Derald lifted the LVL beams up into position. Then Shawn shot some nails to attach the framing to the existing wall.
While the guys worked on the garage wall, Pam and I were inside the basement hanging up more electrical boxes. I went around with the plan and a tape measure marking the location of boxes, and Pam followed hammering in the blue boxes that go on wood framing.
Since our exterior basement walls are insulated concrete forms, the boxes to use there are a little different. We need to cut out the foam to insert a box, and these boxes have a side tab that gets screwed to the plastic "stud" embedded within the foam.
We bought an electric knife to cut the holes, but it gets too hot and melts the foam too fast and makes the hole too big, and looks terrible to boot. So Shawn has to use the sawzall with a very short blade, and looks much better.
The crew worked the rest of the morning on finishing off the soffit on the rest of the eaves. Derald manned the saw, while Shawn installed the soffit. Pam helped the guys on this project as well. They got the soffit installed almost all the way to the front.
Last night, Shawn worked siding the wall up to the soffit, and installed the fascia boards. There's one more piece of fascia that needs to go up, but Shawn needs to finish building the cornice at the front before he can do that.
But you can see Shawn finished the siding up to the soffit, and he actually got the fascia covered. that you see exposed on this picture. He did a really good job on the interior corner. Looks very professional.
Maybe next siding project will be to start on the front gable! The Tyvek is not doing so good, so we're going to have to put another layer of Tyvek to fix a nice tear the wind put in it a couple of weeks ago. But what can you expect when you leave it exposed for so long.
The front gable gets a different style of siding. Intead of lap siding, we'll be using shingles, so that will be a bit trickier to install I think. We also want to have some stone veneer to spruce up the front a bit, but at $100-$150 per sq. ft. on materials, it will probably wait until next year.
Here are the pictures of the refrigerant line for the heat pump. This is before:
This is After:
We still need to fix the hole through the band board, but nothing a little foam can't fix. It is sandable and paintable, so when the exterior gets the second coat of paint, then it will be fine.
Shawn and I will work on getting more electrical boxes installed, and next will be to get the light boxes for ceiling lights and get those up. Then the electrician will come out to mark the route for wires, and we'll drill the holes and channels in the foam for the wires to run to the boxes. We'll also run any coax cables and some telephone/cat5 cables for computer networking.
Then the electrician will come back to run electrical wires. I do believe there's an inspection that needs to be done of the rough-in, and if we get the ok, we should be good to drywall over the electrical. But before drywall, we have to finish installing the thermostats and low-voltage wiring for the radiant heat. As soon as we have electricity for that, we'll fill up the system and test it out.
If that goes ok, then we'll move onto installing the water lines to the kitchen, bath, and laundry and finally we'll be ready for drywall!
Seems close enough to grasp!
Until next time.